VIA flyover, NW approach: foam blocks all in place, rebar getting ready for deck pour, side walls underway.
Progress on SE approach to creek, Transitway and VIA flyover.
Mooney's Bay Station single platform near completion, getting ready to grade and re-install the track / rails.