Snapshot of Carleton Station - May 26, 2021

Photos taken from the elevated parking garage over the O-Train tracks

Snapshot of Lincoln Fields Station - May 16, 2021

Snapshot of Blair Flyover - May 3, 2021

Congratulations to our Stage2LRT team on completing girder installation at the Blair Station to 174 Median Rail Flyover Bridge. Over 4 nights, 21 girders were installed on this important rail bridge for Stage 2 East Extension.

Snapshot of Corso Italia Station - May 3, 2021

Progress on new double-track/platform Corso Italia (Gladstone) Station (not to be confused with the Corso D'Italia Gate near Carling). Note shotcrete to stabilize upper slopes of the widened trench. This area will soon be surrounded by medium and high rises.

Snapshot of Dow's Lake Station - May 3, 2021

More comms work under the future rebuilt Dow's Lake (Carling) Station longer and wider single platform of Trillium Line. Near Corso D'Italia gate.