Work continues to proceed on Line 2 at Bayview Station, constructing the two new platforms, and the future overhead pedestrian bridges that will permit a direct connection to the Trinity development.
Work continues on Line 2 at Bayview Station. Once reopened, it will have 2 platforms, although only 1 will see regular service. A temporary multi-use pathway has been constructed and opened to allow guideway work to proceed. Interestingly, the temporary pathway follows right next to the Line 2 platform through the station, and where the future double tracks will be located.
Work on Line 2 at Bayview Station continues. The east stairway outside of the station is temporarily closing and will be detoured as work continues. A new MUP is also being constructed.
Work is advancing on the new MUP pathway.