Staging area for the assembly of the new pedestrian bridge that will cross the Rideau River, parallel to the O-Train bridge.
Unloading conduit foundation blocks, the Rideau River Bridge and new pedestrian bridge foundation and Carleton Station South underpass and platforms. Slow progress at -12C.
Carleton Station platforms and near side and farside underpasses showing gradual progress.
Getting ready for the ties and double track leading up to the extended station.
Pictures taken from the Carleton University parking garage, showing work on underpass, Station and location of end of double track before the Rideau River.
The White Bridge, all covered up for safe asbestos removal and refurbishment, that crosses the Rideau River at Carleton University, seen from the River Building.
Lots of work taking place around and on the O-Train alignment. In several pictures, you can observe the guideway is covered with crushed rock, creating ramps for easier access to the work sites.