VIA flyover, NW approach: foam blocks all in place, rebar getting ready for deck pour, side walls underway.
Progress on SE approach to creek, Transitway and VIA flyover.
Excavation of top soil just west of Kitchissipi Station to extend the SJAM parkway tunnel/ trench further east to the existing Transitway.
Showing realigned MUP back to the Scott street detour from previous MUP detour over adjacent lands to south used during bridge construction. Adjacent lands site of future proposed 2 tower 12 sty. mid rise residential buildings.
Steel piles being added on Northside of Richmond Road just West of McEwen Ave. Former site of the McEwen gas station.
Stage 2 flyover at Ellwood Junction/Brookfield/Sawmill Creek. Note low profile steel bridge, for ample clearance. Also one side of retaining walls is complete on unstable deep clay overburden.
December 5, 2021
Today a similar Mark IV tamper https://harscorail.com/equipment/surfacing/mark-iv-tamper.html was over legacy Hunt Club bridge. Likely now rails from Walkley yard, through Greenboro, W side of South Keys Station, past Lester Rd to NRC and also towards FlyYOW spur. FLIRT Trillium Stage 2 testing soon?
December 6, 2021
Equipment North of South Key's Station this morning. On a break just now.
December 7, 2021
As of the weekend, one set of rails is in place and being adjusted on the west side of SK Station. Test trains could run from Walkley Yard/Greenboro, over Lester to as far as Leitrim Road!
RELAM 925 doing ballast/tie work behind South Keys Mall for Stage 2
https://relaminc.com/equipment/knox-kershaw-k925s-ballast-regulators/
Fantastic aerial shots of the SJAM parkway O-Train tunnel, that will connect from Kichi Sibi Station to Sherbourne Station. The tunnel is being built cut-and-cover. Once completed, the road will be realigned and a portion will pass on top.
Placing lightweight foam blocks onto foundations over deep marine clay for the new VIA flyover approaches, Trillium Line Stage 2
Looks like all Transitway flyover beams now placed and cleanup activities now in progress. Trillium Line Stage 2.