Snapshot of the Guideway near Pinecrest - December 20, 2023

PXL_20231220_202326566.MP
Continue reading

Snapshot of VIA Rail Flyover - November 16, 2023

F_FLCHSW8AAyRN9
Continue reading

Snapshot of Rideau River bridge - September 12, 2023

PXL_20230912_183925706
Continue reading

Snapshot of the O-Train Line 2 (Northern Segment) Guideway - August 6, 2023

DSC03969
Continue reading

Snapshot of VIA Rail Flyover - May 28, 2023

IMG_3543
Continue reading

Snapshot of the VIA Rail Flyover - May 18, 2023

dji_fly_20230518_141818_620_1684433982994_photo_optimized
Continue reading

Snapshot of the Byron/Richmond Tunnel - October 30, 2022

FgWUKrUXwAQoJKx

Stage 2 Construction at Richmond near Woodroffe Ave!

Continue reading

Snapshot of VIA Rail Flyover - October 24, 2022

Ff1_m-wXkAEBZjf
Continue reading

Snapshot of the VIA Rail Flyover - October 11, 2022

dji_export_1665426206651
Continue reading

Snapshot of VIA Flyover - August 15, 2022

via2

VIA flyover, NW approach: foam blocks all in place, rebar getting ready for deck pour, side walls underway.

Progress on SE approach to creek, Transitway and VIA flyover. 

Continue reading

Snapshot of the 174 from the SGEC Parkway - June 18, 2022

20220618_LRTRailLookingEast
Looking West
Looking East
Continue reading

Snapshot of SJAM Parkway Tunnel - June 24, 2022

dji_export_1656088461485
Continue reading

Snapshot of the Trillium Line VIA flyover - June 5, 2022

dji_export_1654442530519
Continue reading

Snapshot of SJAM Parkway Tunnel - May 20, 2022

FTOobQHWQAoGA1X

Photos taken near Cleary and Richmond Road.

Continue reading

Snapshot of SJAM Parkway Tunnel - April 2, 2022

20220402_113527

 Excavation of top soil just west of Kitchissipi Station to extend the SJAM parkway tunnel/ trench further east to the existing Transitway.

Continue reading

Snapshot of Scott Street Detour Temporary Bridge - March 21, 2022

20220321_132223

Showing realigned MUP back to the Scott street detour from previous MUP detour over adjacent lands to south used during bridge construction. Adjacent lands site of future proposed 2 tower 12 sty. mid rise residential buildings.

Continue reading

Snapshot of Richmond Rd Temporary Bridge at Lincoln Fields - March 26, 2022

20220326_090943

Steel piles being added on Northside of Richmond Road just West of McEwen Ave. Former site of the McEwen gas station.

Continue reading

Snapshot of the Trillium Line VIA flyover - March 17, 2022

FOFQpSsWUAcXQTO

The SE end of the VIA flyover bridge near Brookfield E. 

Stage 2 flyover at Ellwood Junction/Brookfield/Sawmill Creek. Note low profile steel bridge, for ample clearance. Also one side of retaining walls is complete on unstable deep clay overburden. 

Continue reading

Snapshot of VIA Rail and Ellwood Flyovers - December 22, 2021

20220105-195434PXL_20211222_152830370
Continue reading

Snapshot of Rail Tamper near Greenboro and South Keys Stations - December 5-7, 2021

20211215-185746FF3e-ntXMAcP7LO

December 5, 2021

Today a similar Mark IV tamper https://harscorail.com/equipment/surfacing/mark-iv-tamper.html was over legacy Hunt Club bridge. Likely now rails from Walkley yard, through Greenboro, W side of South Keys Station, past Lester Rd to NRC and also towards FlyYOW spur. FLIRT Trillium Stage 2 testing soon?

December 6, 2021

Equipment North of South Key's Station this morning. On a break just now.

December 7, 2021

As of the weekend, one set of rails is in place and being adjusted on the west side of SK Station. Test trains could run from Walkley Yard/Greenboro, over Lester to as far as Leitrim Road!

Continue reading

Snapshot of Ballast and Tie Work near South Keys Station - December 13, 2021

20211215-190926FGgHjE7XoAARcPh

RELAM 925 doing ballast/tie work behind South Keys Mall for Stage 2

https://relaminc.com/equipment/knox-kershaw-k925s-ballast-regulators/

Continue reading

Snapshot of the Sir John A. Macdonald Parkway Tunnel - December 3, 2021

20211206-164210dji_export_1638566221595

 Fantastic aerial shots of the SJAM parkway O-Train tunnel, that will connect from Kichi Sibi Station to Sherbourne Station. The tunnel is being built cut-and-cover. Once completed, the road will be realigned and a portion will pass on top.

Continue reading

Snapshot of the VIA Rail Flyover - November 23, 2021

20211206-155148FE5za3CXsAkMBfn

 Placing lightweight foam blocks onto foundations over deep marine clay for the new VIA flyover approaches, Trillium Line Stage 2

Continue reading

Snapshot of the Transitway Flyover - November 13, 2021

FEGQFneWQAEg7ox

Looks like all Transitway flyover beams now placed and cleanup activities now in progress. Trillium Line Stage 2.

Continue reading

Snapshot of the VIA Rail Flyover - November 15, 2021

FEQPKAlXMAcwjzG

On the NE side of the new VIA flyover, many white foam blocks will be used for the approaches because of the marine/leda clay underlying. The bridge piers were drilled out very deep. Trillium Line Stage 2.

Continue reading