Crews poured a total of 187m3 of cement on the new Blair Station to 174 Median Rail Bridge connecting the existing line to the East Extension.
The White Bridge, all covered up for safe asbestos removal and refurbishment, that crosses the Rideau River at Carleton University, seen from the River Building.
Various views of Trillium Line Stage 2 VIA Rail flyover near Mooneys Bay Station. Note concrete girders added last week, also slope and curve of steel girder span. More spans to come over Transitway and Sawmill Creek.
The new Confederation Line Stage 2 "split" flyover near Lincoln Fields. The MUP bridge will be removed and shifted a bit north for OCS clearance.
Pier foundations for the new shifted MUP bridge. Woodroffe HS in background.
From the flyover bridge at the split, Moodie trains will dive down to a short tunnel under Connaught and cut past the corner of the OCTranspo Pinecrest bus storage ( in background). Then head to new Queensview Station. Roller coaster?
Progress you can see! Stage 2 crews successfully started girder installation on the 300-m long Ellwood Diamond Rail Bridge. This grade separation will allow the O-Train to travel over the VIA Rail line.
Work continues to realign the 174 highway lanes to make room in the median for O-Train guideway construction
The future 4 lane, single track Lester Trillium Line Stage 2 overpass near NRC is complete and rails ready to be installed. Will be a lovely cycling MUP from Brookfield all alongside east far to the south. Guess that level crossing will not be reinstated.
Infrastucture: temporary steel bridge on Woodroffe at Richmond Rd just completed for cut and cover tunnel underneath. This installation will permit excavation and tunneling to take place underneath this section of Woodroffe, without a long duration disruption to vehicle and pedestrian traffic.
Great news! Stage2LRT South Extension crews installed precast concrete arches for the new rail bridge over Mosquito Creek. While the future O-Train travels above, the tunnel below provides ample space for wildlife passage.
From the Brookfield East crossing you can see the line of piers for the Ellwood Junction VIA / creek/ Transitway flyover and the old Trillium Line alignment / bridges.
In preparation for re-laying rails from Brookfield East towards South Keys, Lester and Leitrim, ties and hardware have been delivered.
Mystery solved! The White Bridge of the Trillium Line has been covered in a white tent for environmental safe removal of decades of lead paints, at the Rideau River.
Check this out! Stage 2 crews are making amazing progress on the O-Train East Extension with 14 out of 21 girders installed on the Blair Station to 174 Median Rail Bridge since Wednesday!
Great views of Lincoln Fields station from the distance, showing the size and scope of the work at this expansive and important station that will see a massive transformation over these coming years.
O-Train Station at Bayshore will pass through the existing Transitway area located at the far end of the existing station.
Lincoln Fields will be the western most transfer point for O-Train Lines 1 (to Algonquin) and Line 3 (to Moodie). Trains arriving from the east will emerge from a tunneled guideway into the station. Heading west, the tracks will split to serve both lines, with Line 1 passing underneath Line 3 (which will make use of a rail flyover, as shown in the lower images).
Scenes from the Beech St Bridge, working to widen the trench from Bayview Station/Gladstone and under Queensway, to double the tracks to this point. Single track from here south, through Dow's Lake (Carling) Station to the Carleton Station switch.
Tenting over the "White" Bridge over the Rideau River near Carleton University in prep for pier rehabilitation. New MUP bridge will be just to the right/upstream.
The Lincoln Fields rail flyover, permitting Lines 1 and 3 to diverge to their respective destinations. This photos were taken from a bus riding along the Transitway underneath the structure, in the same way that future O-Train Line 1 will travel.
While taking the photo from the Young Street extension over the Trillium Line, a supervisor was nearby and explained what was taking place. They have one machine driving into the rock from above, then they have the other driller machine that's in the trench dig away from the side. This is part of the work to widen the trench between Corso Italia and Dow's Lake Stations.
As part of the Stage 2 O-Train Trillium Line South Extension project, work is proceeding on the Ellwood Diamond rail bridge, which will allow VIA Rail trains to safely pass below the Trillium Line.