Snapshot Updates

Snapshot of Uplands Station - August 24, 2020

Uplands Bridge progress for Trillium Line Stage 2 / Airport Line. The station will be to the East (left).

Snapshot of Sherbourne Station - August 24, 2020

At Cleary, the Confederation Line it will pass diagonally under Richmond Rd and head west under/along the denuded, formerly treed Britannia Streetcar corridor. In a very expensive cut and cover tunnel. Underground station just west of here at Sherbourne.

Near Cleary Ave, western Confederation Line Stage 2 will leave the expensive double decker Western Ottawa River Parkway structure and head SW here, to cross under Richmond Rd. 

Snapshot of Carleton Station - August 25, 2020

Dragged away almost new switches and signal components etc. for temporary storage and re-use at Carleton Station. 

Carleton Station platforms will be extended to accommodate trains double the length, and the passing siding here greatly lengthened. However frequency will be unchanged and travel times increased due to new Gladstone and Walkley Station stops. 

Snapshot of Limebank Station - August 24, 2020

Limebank Road overpass and terminus, Trillium Line Stage 2. To go west from here to Fallowfield/Strandherd you will need to transfer to bus.

Snapshot of Walkley Station - August 20, 2020

Future Walkley Station single track/platform rails have been lifted and dragged north to accommodate construction work for Stage 2 Trillium Line.