Snapshot Updates

Snapshot of Gladstone Station - June 16, 2020

Construction at Gladstone Station continues with rock cutting and blasting.

Snapshot of Bowesville Station - June 13, 2020

Bowesville Road Trillium Line crossing is now in place.
This installation necessitated an overnight closure of Bowesville Road. A similar installation was also recently completed at Uplands Drive to connect to the Airport.

Snapshot of Gladstone Station - June 5, 2020

Looking North at the future site of Gladstone Station. Tarps have been placed over the soon to be constructed Northbound tracks.
Looking south at the Highway 417 overpass. The rails have been removed and the underpass is now blocked by rocks at the far end.

Snapshot of Gladstone Station - May 30, 2020

Gladstone Station, from the beginning of the MUP detour looking south. Topsoil has been excavated down to bedrock along East of tracks.
Dug trench along the East edge of the former MUP looking south.
Looking West from the MUP detour across the recently contructed staging area towards the future Gladstone Station.
Looking North from the Gladstone Ave. Bridge. Some top soil removed and tracks are removed.

Snapshot of Bowesville Station - May 30, 2020

Bowesville Station elevated pillars to enable a crossing over Bowesville Road. Looking West.
Looking East, towards the future station to be constructed in the background.