Snapshot of the Blair Flyover - April 30, 2021

Check this out! Stage 2 crews are making amazing progress on the O-Train East Extension with 14 out of 21 girders installed on the Blair Station to 174 Median Rail Bridge since Wednesday! 

Snapshot of Lincoln Fields Station - April 24, 2021

Tunnel Infrastructure piling and excavation preparation.

Looking west N. Side Richmond Road towards McEwen Ave.
Looking East from McEwen Ave.
Looking south From Richmond Rd. towards Lincoln Fields.
Looking West from Lincoln Fields at SJAM parkway towards Richmond Rd. future Tunnel curve.

Snapshot of Sherbourne Station - April 24, 2021

Tunnel excavation

Utility work. Piling and excavation work along the corridor. 

Snapshot of Uplands Station - April 25, 2021

Concrete pouring and formation continue to take place at Uplands. The elevated track alignment is getting closer to completion and potentially ready for track installation once concrete pouring will be done for the station frame. Fencing is being installed alongside the future trackway. The rail-over-road overpass at Upland and Airport Parkway are practically complete with their approaches being completed and smoothed down.

Snapshot of Greenboro Station - April 27, 2021

The short simple wood and gravel Greenboro Station single platform are being doubled in length with steel and concrete on foam platforms.